Commencement of work. The applicant or the applicant’s agent must notify the Department of Public Works construction inspection office not less than 48 hours prior to commencing the work authorized by the right of way permit.

Commencement of concrete or asphalt paving. The applicant or the applicant’s agent must notify the Department of Public Works construction inspection office not less than 48 hours in advance of the application of any type of concrete or asphalt paving. The Director may stop or delay paving operations when the weather or other conditions indicate that suitable results cannot be obtained. (Ord. M-4026 §11, 2012)